The railway has a short elevated section which forms one of the ends of the line. I had originally planned to use lightweight concrete blocks to make the track bed but decided that it wouldnt look very nice so I used wood to build this section with the view to replace it with better quality materials at a later date.
This has lasted very well for something that  used materials I happened to have lying around but it has finally got to a point where it needs replacement.

The pictures show the demolition in progress.
This view shows the construction of the beam made of plywood with wooden blocks between them, supported on plastic pipe columns with a wooden baseboard on top.
The wood on the top was recycled pallet's and has now warped beyond use.
The middle of the curve used a short length of wood to bridge the gap as I didnt have enough plywood.
The plywood at this end of the section was totally de-laminated and fell apart as I touched it. 
The chasm that will be filled tomorrow 